Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

how do you balance __H2SO4 + __B(OH)3 --> __B2(SO4)3 + __H2O
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?
What are the advantages and disadvantages of globalization
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?
how do you balance __H2SO4 + __B(OH)3 --> __B2(SO4)3 + __H2O
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?
how do you balance __H2SO4 + __B(OH)3 --> __B2(SO4)3 + __H2O