An average of 2,000 charts need to be coded each month. if it takes an average of 15 minutes to code each chart— how many charts does the average coder code per 8-hour day?

Respuesta :

Bea1111 Bea1111
  • 01-05-2017
Put 8 hours into minutes which is 60•8= 480.
Then divide 480 by 15 to find how many charts are coded in 8 hours by a coder.
480/15= 32.

So the average worker codes 32 charts per 8-hour work day.
Answer Link

Otras preguntas

SOMEONE PLEASE ANSWER‼️‼️‼️ILL MARK BRAINLYEST PLEASE ‼️‼️ In the triangle LMN, LM = 13, MN = 17, LN = 10. Which is the largest angle? A. LNM B. LMN C. This can
Jason was a recent graduate from a university program with a Bachelor of Science in Medical Technology. He will begin a position at the local hospital working 4
How can the president check the power of Congress?
NOT SURE HELPP... it's a khan academy question
Describe the structure and parts of DNA molecule
which ordered pair represents the coordinate of point h? (0.6, - 1.4) (-1.4, 0.6) (-1.2 , 0.3) (0.3, - 1.2)
Las senoras blank unos helados tango
Solve the proportion. 5/9=g/27
Pls help me asap!! Only answer if u know the correct answer! Thanks! :)
Click to review the online content. Then answer the question below, using complete sentences. Scroll down to view additional questions. Online Content: Site 1 O