In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

1. welcher satz ist richtig? a. ich weiss nicht, ob er hat sein zimmer aufgeraumt. b. ich weiss nicht, ob hat sein zimmer hat aufgeraumt. c. ich weiss nicht, o
When was the Great Depression and how long did it last?
Which question is being answered by the adverb modifier in the sentence below: Her blue eyes sparkled brilliantly in the sunlight. a. Where? c. In what way? b.
Options A. 7 B. 9 C. 21 D. 24
What graph best represents the solution to the inequality y−2x>−8
At a local company, the ages of all new employees hired during the last 10 years are normally distributed. The mean age is 32 years old, with a standard deviati
Need help with this
what is the expression for the difference between five times a number and twice that number?​
If a deer consumes 500 kg of primary producer (grass, trees, etc). How much of this is incorporated into the biomass of the deer? Your answer: a. 5 kg b
The disks of spiral galaxies appear blue because