Determine the amount of work done when a crane lifts a 100-N block form 2m above the ground to 6m above the ground

Respuesta :

hrzlatevski
hrzlatevski hrzlatevski
  • 03-02-2019

Data given:

F=100N

Δx=6m-2m=4m

A=?

Formula needed:

A=F×s

Solution:

A=100N×4m

A=400J

Answer Link

Otras preguntas

find the proportionality of y=7.25x
Solve proportions 13/25 = p/100
There were 149 angelfish and goldfish in an aquarium.  There were twice as many guppies as angelfish.  After selling 35 goldfish there are half as many goldfish
There were 149 angelfish and goldfish in an aquarium.  There were twice as many guppies as angelfish.  After selling 35 goldfish there are half as many goldfish
Write the number that matches the clues My number has 2 hundreds. The tens digit is 9 more than the ones digit
plz help with this french hw plzzz
which term better describes political parties in american politics: division or unifying?
There were 149 angelfish and goldfish in an aquarium.  There were twice as many guppies as angelfish.  After selling 35 goldfish there are half as many goldfish
How would you describe the human features of a place?
Which three countries have the least access to technology?